Dubai Islands handover tracker

At a glance

Handovers are staggered. Some buildings are in a 2026 window; a large middle group is 2027–28; later phases run into 2029. This table is a reading list of published windows, not a RERA certificate and not a site-visit log.

Figures below are from developer materials and secondary market pages, dated in Source. Status will move. Confirm on Dubai REST / the developer before you reserve.

ProjectDeveloperIslandTypePublished handover windowNotesSource / as-of
Azura ResidencesNakheelCentral (verify)Apartments2026 window often quoted as Q2 2026Early apartment keysBroker/developer pages, treat as quoted
Bay VillasNakheelNot confirmed on Elite on this siteVillas / townhouses2027 window often quoted as Q2 2027Villa productQuoted
Bay Grove ResidencesNakheelWaterfront — island TBD on this siteApartmentsLate 2028 (phases 1–3), Q2 2029 (phase 4)All 1,154 homes under main contract as of 26 Oct 2026.Nakheel press release, 26 Oct 2026
Rixos residencesNakheel / Rixos brandTBD — confirmBranded apartmentsLater-2026 window often citedDLD-registered completion date of 15 Oct 2026 (per a registry tracker) has passed. Nakheel 14 Sep 2026 inspection still 71.21% Bay / 42.61% Beach-Hotel. No revised handover date found. Late 2026 looks unlikely — confirm with Nakheel in writing. Status: delayed vs registered date.Nakheel construction progress, 14 Sep 2026; DXB Realtor registry tracker — registered completion 15 Oct 2026
Flora IsleNakheelTBD — confirmApartments2028 window often quoted as Q1 2028Off-planQuoted

How to use this

Pair project with site visit and Dubai REST app. A published quarter is not keys in hand.

What we will not put here

Sold-out marketing, invented % complete, or a single year for the whole community.